Business School Building - Projected Construction Timeline

Projected Construction Timeline

After fund-raising for the $48 million project is completed, the University will break ground for the new Business School building near the existing Arts & Sciences building on Palm Drive.

Below is the projected timeline for construction:

Month 1 Submit plans to governmental agencies
Month 1 through 3 Site preparation (close parking lots, conduct archeological work, relocate existing utilities, etc)
Month 4 Receive approval on permits
Month 6 Grading begins
Month 7 Foundation slab poured 
Month 9 Steel framing begins 
Month 11 Enclosure completed
Month 12 Interior work (walls, flooring)
Month 16  Exterior work (landscaping, signage)
Month 18  Move in and activation 
Month 21 Opening celebration