Angel v. Murray
113 R.I. 482 (R.I. 1974)
Roberts, J.
This is a civil action brought by Alfred L. Angel
and others against John E. Murray, Jr., Director of Finance of the City of Newport, the
city of Newport, and James L. Maher, alleging that Maher had illegally been paid the sum
of $20,000 by the Director of Finance and praying that the defendant Maher be ordered to
repay the city such sum. The case was heard by a justice of the Superior Court, sitting
without a jury, who entered a judgment ordering Maher to repay the sum of $20,000 to the
city of Newport. Maher is now before this court prosecuting an appeal.
The record discloses that Maher has provided the city of
Newport with a refuse-collection service under a series of five-year contracts beginning
in 1946. On March 12, 1964, Maher and the city entered into another such contract for a
period of five years commencing on July 1, 1964, and terminating on June 30, 1969. The
contract provided, among other things, that Maher would receive $137,000 per year in
return for collecting and removing all combustible and noncombustible waste materials
generated within the city.
In June of 1967 Maher requested an additional $10,000 per year
from the city council because there had been a substantial increase in the cost of
collection due to an unexpected and unanticipated increase of 400 new dwelling units.
Maher's testimony, which is uncontradicted, indicates the 1964 contract had been
predicated on the fact that since 1946 there had been an average increase of 20 to 25 new
dwelling units per year. After a public meeting of the city council where Maher explained
in detail the reasons for his request and was questioned by members of the city council,
the city council agreed to pay him an additional $10,000 for the year ending on June 30,
1968. Maher made a similar request again in June of 1968 for the same reasons, and
the city council again agreed to pay an additional $10,000 for the year ending on June 30,
1969.
The trial justice found that each such $ 10,000 payment was made
in violation of law. His decision, as we understand it, is premised on two independent
grounds. First, he found that the additional payments were unlawful because they had not
been recommended in writing to the city council by the city manager. Second, he found that
Maher was not entitled to extra compensation because the original contract already
required him to collect all refuse generated within the city and, therefore, included the
400 additional units. The trial justice further found that these 400 additional units were
within the contemplation of the parties when they entered into the contract. It appears
that he based this portion of the decision upon the rule that Maher had a preexisting duty
to collect the refuse generated by the 400 additional units, and thus there was no
consideration for the two additional payments.
I. [The court concluded that provisions of the Charter for the City of Newport did
not preclude the city council's action in amending the contract.]
II.
Having found that the city council had the power to modify the
1964 contract without the written recommendation of the city manager, we are still
confronted with the question of whether the additional payments were illegal because they
were not supported by consideration.
A.
As previously stated, the city council made two $10,000 payments.
The first was made in June of 1967 for the year beginning on July 1, 1967, and ending on
June 30, 1968. Thus, by the time this action was commenced in October of 1968, the
modification was completely executed. That is, the money had been paid by the city
council, and Maher had collected all of the refuse. Since consideration
is only a test of the enforceability of executory promises, the presence or absence of
consideration for the first payment is unimportant because the city council's agreement to
make the first payment was fully executed at the time of the commencement of this action.
However, since both payments were made under similar circumstances, our decision regarding
the second payment (Part B, infra) is fully applicable to the first payment.
B.
It is generally held that a modification of a contract is itself
a contract, which is unenforceable unless supported by consideration. . . . . In Rose
v. Daniels, 8 R. I. 381 (1866), this court held that an agreement by a debtor with a
creditor to discharge a debt for a sum of money less than the amount due is unenforceable
because it was not supported by consideration.
Rose is a perfect example of the preexisting duty rule.
Under this rule an agreement modifying a contract is not supported by consideration if one
of the parties to the agreement does or promises to do something that he is legally
obligated to do or refrains or promises to refrain from doing something he is not legally
privileged to do, . . . In Rose there
was no consideration for the new agreement because the debtor was already legally
obligated to repay the full amount of the debt.
Although the preexisting duty rule is followed by most
jurisdictions, a small minority of jurisdictions, Massachusetts, for example, find that
there is consideration for a promise to perform what one is already legally obligated to
do because the new promise is given in place of an action for damages to secure
performance. See Swartz v. Lieberman, 323 Mass. 109, 80 N.E.2d 5 (1948); Munroe
v. Perkins, 26 Mass. (9 Pick.) 298 (1830). Swartz is premised on the
theory that a promisor's forbearance of the power to breach his original agreement and be
sued in an action for damages is consideration for a subsequent agreement by the promisee
to pay extra compensation. This rule, however, has been widely criticized as an anomaly.
The primary purpose of the preexisting duty rule is to prevent
what has been referred to as the "hold-up game." A classic example of the
"hold-up game" is found in Alaska Packers' Ass'n v. Domenico, 117
F. 99 (9th Cir. 1902). There 21 seamen entered into a written contract with Domenico to
sail from San Francisco to Pyramid Harbor, Alaska. They were to work as sailors and
fishermen out of Pyramid Harbor during the fishing season of 1900. The contract specified
that each man would be paid $50 plus two cents for each red salmon he caught. Subsequent
to their arrival at Pyramid Harbor, the men stopped work and demanded an additional $50.
They threatened to return to San Francisco if Domenico did not agree to their demand.
Since it was impossible for Domenico to find other men, he agreed to pay the men an
additional $50. After they returned to San Francisco, Domenico refused to pay the men an
additional $50. The court found that the subsequent agreement to pay the men an additional
$50 was not supported by consideration because the men had a preexisting duty to work on
the ship under the original contract, and thus the subsequent agreement was unenforceable.
Another example of the "hold-up game" is found in the
area of construction contracts. Frequently, a contractor will refuse to complete work
under an unprofitable contract unless he is awarded additional compensation. The courts
have generally held that a subsequent agreement to award additional compensation is
unenforceable if the contractor is only performing work which would have been required of
him under the original contract. . . .
These examples clearly illustrate that the courts will not
enforce an agreement that has been procured by coercion or duress and will hold the
parties to their original contract regardless of whether it is profitable or unprofitable.
However, the courts have been reluctant to apply the pre-existing duty rule when a party
to a contract encounters unanticipated difficulties and the other party, not influenced by
coercion or duress, voluntarily agrees to pay additional compensation for work already
required to be performed under the contract. For example, the courts have found that
the original contract was rescinded, Linz v. Schuck, 106 Md. 220, 67 A. 286
(1907); abandoned, Connelly v. Devoe, 37 Conn. 570 (1871), or waived, Michaud
v. MacGregor, 61 Minn. 198, 63 N.W. 479 (1895).
Although the preexisting duty rule has served a useful purpose
insofar as it deters parties from using coercion and duress to obtain additional
compensation, it has been widely criticized as a general rule of law. With regard to the
preexisting duty rule, one legal scholar has stated: "There has been a growing
doubt as to the soundness of this doctrine as a matter of social policy. * * * In certain
classes of cases, this doubt has influenced courts to refuse to apply the rule, or to
ignore it, in their actual decisions. Like other legal rules, this rule is in process of
growth and change, the process being more active here than in most instances. The result
of this is that a court should no longer accept this rule as fully established. It should
never use it as the major premise of a decision, at least without giving careful thought
to the circumstances of the particular case, to the moral deserts of the parties, and
to the social feelings and interests that are involved. It is certain that the rule,
stated in general and all-inclusive terms, is no longer so well-settled that a court must
apply it though the heavens fall." 1A Corbin, supra, § 171; see also
Calamari & Perillo, supra, § 61.
The modern trend appears to recognize the necessity that courts
should enforce agreements modifying contracts when unexpected or unanticipated
difficulties arise during the course of the performance of a contract, even though there
is no consideration for the modification, as long as the parties agree voluntarily.
Under the Uniform Commercial Code, § 2-209(1), which has been
adopted by 49 states, "[an] agreement modifying a contract [for the sale of goods]
needs no consideration to be binding." Although at first blush this section appears
to validate modifications obtained by coercion and duress, the comments to this section
indicate that a modification under this section must meet the test of good faith imposed
by the Code, and a modification obtained by extortion without a legitimate commercial
reason is unenforceable.
The modern trend away from a rigid application of the preexisting
duty rule is reflected by § 89D(a) of the American Law Institute's Restatement Second of
the Law of Contracts, which provides: "A promise modifying a
duty under a contract not fully performed on either side is binding (a) if the
modification is fair and equitable in view of circumstances not anticipated by the parties
when the contract was made * * *."
We believe that § 89D(a) is the proper rule of law and find
it applicable to the facts of this case. It not only prohibits modifications obtained by
coercion, duress, or extortion but also fulfills society's expectation that agreements
entered into voluntarily will be enforced by the courts. Section 89D(a), of course,
does not compel a modification of an unprofitable or unfair contract; it only enforces a
modification if the parties voluntarily agree and if (1) the promise modifying the
original contract was made before the contract was fully performed on either side, (2) the
underlying circumstances which prompted the modification were unanticipated by the
parties, and (3) the modification is fair and equitable.
The evidence, which is uncontradicted, reveals that in June of
1968 Maher requested the city council to pay him an additional $10,000 for the year
beginning on July 1, 1968, and ending on June 30, 1969. This request was made at a public
meeting of the city council, where Maher explained in detail his reasons for making the
request. Thereafter, the city council voted to authorize the Mayor to sign an amendment to
the 1954 contract which provided that Maher would receive an additional $10,000 per year
for the duration of the contract. Under such circumstances we have no doubt that the city
voluntarily agreed to modify the 1964 contract.
Having determined the voluntariness of this agreement, we turn
our attention to the three criteria delineated above. First, the modification was made in
June of 1968 at a time when the five-year contract which was made in 1964 had not been
fully performed by either party. Second, although the 1964 contract provided that Maher
collect all refuse generated within the city, it appears this contract was premised on
Maher's past experience that the number of refuse-generating units would increase at a
rate of 20 to 25 per year. Furthermore, the evidence is uncontradicted that the 1967-1968
increase of 400 units "went beyond any previous expectation." Clearly, the
circumstances which prompted the city council to modify the 1964 contract were
unanticipated. Third, although the evidence does not indicate what proportion of the total
this increase comprised, the evidence does indicate that it was a "substantial"
increase. In light of this, we cannot say that the council's agreement to pay Maher the
$10,000 increase was not fair and equitable in the circumstances.
The judgment appealed from is reversed, and the cause is remanded
to the Superior Court for entry of judgment for the defendants.