Austin Instrument, Inc. v. Loral Corporation
29 N.Y.2d 124 (N.Y. Ct. of Appeals 1971)
Fuld, J.
The defendant, Loral Corporation, seeks to recover payment
for goods delivered under a contract which it had with plaintiff Austin Instrument, Inc.,
on the ground that the evidence establishes, as a matter of law, that it was forced
to agree to an increase in price on the items in question under circumstances amounting to
economic duress.
In July of 1965, Loral was awarded a $6,000,000 contract by the
Navy for the production of radar sets. The contract contained a schedule of deliveries, a liquidated damages clause applying to late
deliveries and a cancellation clause in case of default by Loral. The latter thereupon
solicited bids for some 40 precision gear components needed to produce the radar sets, and
awarded Austin a subcontract to supply 23 such parts. That party commenced delivery in
early 1966.
In May, 1966, Loral was awarded a second Navy contract for the
production of more radar sets and again went about soliciting bids. Austin bid on all 40
gear components but, on July 15, a representative from Loral informed Austin's president,
Mr. Krauss, that his company would be awarded the subcontract only for those items on
which it was low bidder. The Austin officer refused to accept an order for less than all
40 of the gear parts and on the next day he told Loral that Austin would cease deliveries
of the parts due under the existing subcontract unless Loral consented to substantial
increases in the prices provided for by that agreement -- both retroactively for parts
already delivered and prospectively on those not yet shipped -- and placed with Austin the
order for all 40 parts needed under Loral's second Navy contract. Shortly thereafter,
Austin did, indeed, stop delivery. After contacting 10 manufacturers of precision gears
and finding none who could produce the parts in time to meet its commitments to the Navy,
Loral acceded to Austin's demands; in a letter dated July 22, Loral wrote to Austin that
"We have feverishly surveyed other sources of supply and find that because of the
prevailing military exigencies, were they to start from scratch as would have to be the
case, they could not even remotely begin to deliver on time to meet the delivery
requirements established by the Government. * * * Accordingly, we are left with no choice
or alternative but to meet your conditions."
Loral thereupon consented to the price increases insisted upon by
Austin under the first subcontract and the latter was awarded a second subcontract making
it the supplier of all 40 gear parts for Loral's second contract with the Navy. n2 Although Austin was granted until September to resume
deliveries, Loral did, in fact, receive parts in August and was able to produce the radar
sets in time to meet its commitments to the Navy on both contracts. After Austin's last
delivery under the second subcontract in July, 1967, Loral notified it of its intention to
seek recovery of the price increases.
On September 15, 1967, Austin instituted this action against
Loral to recover an amount in excess of $17,750 which was still due on the second
subcontract. On the same day, Loral commenced an action against Austin claiming damages of
some $22,250 -- the aggregate of the price increases under the first subcontract -- on the
ground of economic duress. The two actions were consolidated and, following a trial,
Austin was awarded the sum it requested and Loral's complaint against Austin was dismissed
on the ground that it was not shown that "it could not have obtained the items in
question from other sources in time to meet its commitment to the Navy under the first
contract." A closely divided Appellate Division affirmed. There was no material
disagreement concerning the facts; as Justice Steuer stated in the course of his dissent
below, "[the] facts are virtually undisputed, nor is there any serious question of
law. The difficulty lies in the application of the law to these facts."
The applicable law is clear and, indeed, is not disputed by the
parties. A contract is voidable on the ground of duress when it is established that
the party making the claim was forced to agree to it by means of a wrongful threat
precluding the exercise of his free will. The existence of economic duress or
business compulsion is demonstrated by proof that "immediate possession of needful
goods is threatened" or, more particularly, in cases such as the one before us, by
proof that one party to a contract has threatened to breach the agreement by withholding
goods unless the other party agrees to some further demand. However, a mere threat
by one party to breach the contract by not delivering the required items, though wrongful,
does not in itself constitute economic duress. It must also appear that the threatened
party could not obtain the goods from another source of supply and that the ordinary
remedy of an action for breach of contract would not be adequate.
We find without any support in the record the conclusion reached
by the courts below that Loral failed to establish that it was the victim of economic
duress. On the contrary, the evidence makes out a classic case, as a matter of law, of
such duress.
It is manifest that Austin's threat -- to stop deliveries unless
the prices were increased -- deprived Loral of its free will. As bearing on this, Loral's
relationship with the Government is most significant. As mentioned above, its contract
called for staggered monthly deliveries of the radar sets, with clauses calling for
liquidated damages and possible cancellation on default. Because of its production
schedule, Loral was, in July, 1966, concerned with meeting its delivery requirements in
September, October and November, and it was for the sets to be delivered in those months
that the withheld gears were needed. Loral had to plan ahead, and the substantial
liquidated damages for which it would be liable, plus the threat of default, were genuine
possibilities. Moreover, Loral did a substantial portion of its business with the
Government, and it feared that a failure to deliver as agreed upon would jeopardize its
chances for future contracts. These genuine concerns do not merit the label
"'self-imposed, undisclosed and subjective'" which the Appellate Division
majority placed upon them. It was perfectly reasonable for Loral, or any other party
similarly placed, to consider itself in an emergency, duress situation.
Austin, however, claims that the fact that Loral extended its
time to resume deliveries until September negates its alleged dire need for the parts. A
Loral official testified on this point that Austin's president told him he could deliver
some parts in August and that the extension of deliveries was a formality. In any event,
the parts necessary for production of the radar sets to be delivered in September were
delivered to Loral on September 1, and the parts needed for the October schedule were
delivered in late August and early September. Even so, Loral had to "work * * *
around the clock" to meet its commitments. Considering that the best offer Loral
received from the other vendors it contacted was commencement of delivery sometime in
October, which, as the record shows, would have made it late in its deliveries to the Navy
in both September and October, Loral's claim that it had no choice but to accede to
Austin's demands is conclusively demonstrated.
We find unconvincing Austin's contention that Loral, in order to
meet its burden, should have contacted the Government and asked for an extension of its
delivery dates so as to enable it to purchase the parts from another vendor. Aside
from the consideration that Loral was anxious to perform well in the Government's eyes, it
could not be sure when it would obtain enough parts from a substitute vendor to meet its
commitments. The only promise which it received from the companies it contacted was for commencement
of deliveries, not full supply, and, with vendor delay common in this field, it would have
been nearly impossible to know the length of the extension it should request. It must be
remembered that Loral was producing a needed item of military hardware. Moreover, there is
authority for Loral's position that nonperformance by a subcontractor is not an excuse for
default in the main contract. In light of all this, Loral's claim should not be held
insufficiently supported because it did not request an extension from the Government.
Loral, as indicated above, also had the burden of demonstrating
that it could not obtain the parts elsewhere within a reasonable time, and there can be no
doubt that it met this burden. The 10 manufacturers whom Loral contacted
comprised its entire list of "approved vendors" for precision gears, and
none was able to commence delivery soon enough. As Loral was producing a highly
sophisticated item of military machinery requiring parts made to the strictest engineering
standards, it would be unreasonable to hold that Loral should have gone to other vendors,
with whom it was either unfamiliar or dissatisfied, to procure the needed parts. As
Justice Steuer noted in his dissent, Loral "contacted all the manufacturers whom it
believed capable of making these parts" and this was all the law requires.
It is hardly necessary to add that Loral's normal legal remedy of
accepting Austin's breach of the contract and then suing for damages would have been
inadequate under the circumstances, as Loral would still have had to obtain the gears
elsewhere with all the concomitant consequences mentioned above. In other words, Loral
actually had no choice, when the prices were raised by Austin, except to take the gears at
the "coerced" prices and then sue to get the excess back.
Austin's final argument is that Loral, even if it did enter into
the contract under duress, lost any rights it had to a refund of money by waiting until
July, 1967, long after the termination date of the contract, to disaffirm it. It is true that one who would recover moneys allegedly paid under
duress must act promptly to make his claim known. In this case, Loral delayed making its
demand for a refund until three days after Austin's last delivery on the second
subcontract. Loral's reason -- for waiting until that time -- is that it feared another
stoppage of deliveries which would again put it in an untenable situation. Considering
Austin's conduct in the past, this was perfectly reasonable, as the possibility of an
application by Austin of further business compulsion still existed until all of the
parts were delivered.
In sum, the record before us demonstrates that Loral agreed to
the price increases in consequence of the economic duress employed by Austin.
Accordingly, the matter should be remanded to the trial court for a computation of its
damages.
The order appealed from should be modified, with costs, by
reversing so much thereof as affirms the dismissal of defendant Loral Corporation's claim
and, except as so modified, affirmed.
Bergan, J. (dissenting).
Whether acts charged as constituting economic
duress produce or do not produce the damaging effect attributed to them is normally a
routine type of factual issue.
Here the fact question was resolved against Loral both by the
Special Term and by the affirmance at the Appellate Division. It should not be open for
different resolution here.
In summarizing the Special Term's decision and its own, the
Appellate Division decided that "the conclusion that Loral acted deliberately and
voluntarily, without being under immediate pressure of incurring severe business reverses,
precludes a recovery on the theory of economic duress"
When the testimony of the witnesses who actually took part in the
negotiations for the two disputing parties is examined, sharp conflicts of fact emerge.
Under Austin's version the request for a renegotiation of the existing contract was based
on Austin's contention that Loral had failed to carry out an understanding as to the items
to be furnished under that contract and this was the source of dissatisfaction which led
both to a revision of the existing agreement and to entering into a new one.
This is not necessarily and as a matter of law to be held
economic duress. On this appeal it is needful to look at the facts resolved in favor of
Austin most favorably to that party. Austin's version of events was that a threat was not
made but rather a request to accommodate the closing of its plant for a customary vacation
period in accordance with the general understanding of the parties.
Moreover, critical to the issue of economic duress was the
availability of alternative suppliers to the purchaser Loral. The demonstration is replete
in the direct testimony of Austin's witnesses and on cross-examination of Loral's
principal and purchasing agent that the availability of practical alternatives was a
highly controverted issue of fact. On that issue of fact the explicit findings
made by the Special Referee were affirmed by the Appellate Division. Nor is the issue of
fact made the less so by assertion that the facts are undisputed and that only the
application of equally undisputed rules of law is involved.
Austin asserted and Loral admitted on cross-examination that
there were many suppliers listed in a trade registry but that Loral chose to rely only on
those who had in the past come to them for orders and with whom they were familiar. It
was, therefore, at least a fair issue of fact whether under the circumstances such conduct
was reasonable and made what might otherwise have been a commercially understandable
renegotiation an exercise of duress.
The order should be affirmed.