Lafayette Place Associates v. Boston Redevelopment Authority
427 Mass. 509, 694 N.E.2d 820 (Mass. 1998), cert den. 525 U.S. 1177 (1999)
Fried, J.
A jury found the defendants, the city of Boston (city) and the
Boston Redevelopment Authority (BRA), liable for monetary damages for having breached a
contract with the plaintiff, Lafayette Place Associates (LPA), for the sale of certain
land (Hayward Parcel), and the BRA liable for the tort of intentional interference with
LPA's contractual relation with another entity, Campeau Massachusetts, Inc. (Campeau). The
trial judge entered judgment against the city, and granted judgment notwithstanding the
verdict in favor of the BRA, on the ground that it was not amenable to suit for an
intentional tort. We conclude that there was a valid contract between the city and LPA but
that the city did not breach it. We also affirm the judgment entered in favor of the BRA,
and the dismissal of LPA's claims under G. L. c. 93A.
I
This dispute arises out of efforts going back to the administration of
Boston Mayor Kevin White in the late 1970's to rehabilitate the "Combat Zone," a
dilapidated area adjacent to a shopping area on Washington Street. A grand scheme was
devised by LPA's entrepreneurs for the construction of a department store, a retail mall,
and a hotel in the area. In 1978, an agreement (Tripartite Agreement) was signed between
LPA, the city, and the BRA for the development of the area in two phases. Phase I was to
encompass a shopping mall and a hotel and was eventually built. It is not a subject of
these suits. Phase II was to include one or more office buildings, further retail space,
and a department store. It was to be built on four parcels of land to be assembled into a
single parcel, called the Hayward Parcel, at the time partially occupied by a city parking
structure, the Hayward Place parking garage. Whether Phase II would ever be undertaken was
made contingent in the Tripartite Agreement on the city's decision to remove the parking
structure. If it did, the city would still be allowed to build an underground parking
garage on the site with LPA being granted air rights to build over it.
The agreement as to the development of the Hayward Parcel was
principally set out in Section 6.02 of the Tripartite Agreement. Section 6.02 is expressed
in terms of the grant of an option to LPA to purchase the Hayward Parcel. The option is
contingent on notice by the city that it plans to discontinue the Hayward Place garage. By
agreement, LPA could thereupon notify the city within the option period if it
"desires to purchase the rights hereby made available to it [and] the City shall sell
the same . . . ." The Tripartite Agreement and accompanying maps identify the
boundaries of the Hayward Parcel, but indicate several alternatives concerning the rights
to be conveyed. In the Tripartite Agreement, the city is stated to have in hand appraisals
of the fair market value of two of the four component parcels of the Hayward Parcel, and
agrees "forthwith" to obtain appraisals of the two remaining parcels. The price
to be paid was to be one-half of the appraised fair market value as of 1978, plus one-half
of the increase in value attributable to "the construction of the Public Improvements
and the Project." In other words, the formula accounted for the possibility
that between 1978 and the future sale of the Hayward Parcel, the value of the parcel could
change as a result of the construction of Phase I on adjacent land. The Tripartite
Agreement further provided that "the existence and amount of increase in fair market
values attributable to the construction of the Public Improvements and the Project shall
be determined by independent appraisal." Section 13.01 of the Tripartite Agreement
also provides, after giving a standard definition of fair market value, that such value
shall be determined by a procedure, akin to arbitration, by which by giving written notice
either party may designate a first appraiser, the other party designate a second
appraiser, and a third appraiser be appointed by the first and second, by the Chief Judge
of the United States District Court for the District of Massachusetts, or by the president
of the Boston Bar Association.
The Tripartite Agreement also provides,
"the Developer may exercise the right and option set forth in this Section 6.02 by giving notice of its desire to purchase such rights to the City at any time within the Option Period. After the receipt of and following such notice from the Developer, the parties shall in good faith negotiate and enter into an agreement calling for the purchase and sale of the rights in question. Such agreement shall be in the customary form of agreements for the purchase and sale of real estate in the greater Boston area except that the agreement shall reflect such reservation and shall contain other appropriate provisions with respect to the integration of construction and other matters relevant to coordinated use of the rights conveyed and the rights retained by the City."
On February 26, 1982, the parties agreed, in what is known as the Second Supplemental Agreement, to certain changes to the Tripartite Agreement concerning the construction and operation of a parking garage by the city under the Hayward Parcel. In addition, the parties amended Section 6.02 by adding the following:
"If the Developer shall exercise the right and option set forth in this Section 6.02, there shall automatically be created an agreement by the Developer to buy and by the City to sell the . . . Parcels . . . . Appropriate details of the purchase and sale shall be worked out by the parties so as to conform to their intent under this Section 6.02., but if they shall be unable to do so then the matter shall be resolved by arbitration in accordance with the arbitration procedure set forth in ARTICLE EIGHT of the Deed and Agreement, dated as of September 11, 1979, between the City and the Developer."
Article 8 of the deed sets out a binding arbitration procedure for
the resolution of disputes. On December 16, 1983, the city gave notice to LPA that it
intended to discontinue the Hayward Place Garage and build a parking garage beneath the
Hayward Parcel, thereby commencing LPA's option period. In that notice, the city listed
five contingencies to closing the sale of the Hayward Parcel, including that "the
parties are able to agree, via appraisals, on the increased value of parcels D-1, D-2 and
D-3, as the result of the construction of the Lafayette Place Project."
On July 2, 1986, as all parties agree, LPA exercised its option to
purchase the Hayward Parcel. On October 27, 1987, the parties extended the date on which
closing might take place by providing, in what is known as the Third Supplemental
Agreement, that:
"Section 6.02 of the Tripartite Agreement is amended by deleting the proviso in the fourth full paragraph thereof . . . and substituting in its place the following: 'provided that, unless the City and the Developer shall agree to a further extension, the Developer shall lose its rights hereunder to proceed with an acquisition if a closing has not occurred by January 1, 1989, unless the City and/or the Authority shall fail to work in good faith with the Developer through the design review process to conclude a closing."
By virtue of the Third Supplemental Agreement, LPA had until January
1, 1989, a date which all parties refer to as the "drop dead date," to
"proceed with an acquisition."
LPA never demanded and the city never tendered a deed within the
required time period or at any other time. The basis of its contract action against the
city is that the city in bad faith failed to carry out those of its obligations under the
Tripartite Agreement necessary to allow LPA to proceed to demand a closing, and indeed
that it engaged in bad faith actions designed to impede LPA in effecting a timely closing.
The reason for these obstructionist tactics by the city, as LPA sought to show by
testimony and documents, was that the new administration of Mayor Raymond Flynn believed
that the price established by the Section 6.02 formula, which was based on 1978 values,
was grossly unfair to the city in the light of a strong surge in real estate prices in the
intervening years. LPA offered evidence of several instances of what it claimed were the
city's obstructionist tactics. These included failing to complete the appraisals necessary
to establish the price for the Hayward Parcel, initiating zoning changes that would have
greatly reduced the allowable height of the office towers planned for the site, lack of
cooperation about determining whether Avenue de Lafayette and New Essex Street would be
closed, and threatening to put a new street through the middle of the parcel, which would
have made its development economically unviable.
In November, 1987, after the conclusion of the Third Supplemental
Agreement but before the final breakdown of dealings in 1989, LPA negotiated the sale of
its development rights in the Hayward Parcel to Campeau. LPA was to receive $24.5 million
in return for its rights under Phase I of the project. The sale was subject to approval by
the BRA, and on December 4, 1987, LPA filed an application for approval. On February 1,
1988, LPA withdrew its application; the BRA had not acted on it in the interim. In March,
1988, LPA entered into a lease agreement with Campeau whereby Campeau assumed LPA's debts
under Phase I and was to pay LPA approximately $21.5 million in cash and notes in return
for LPA's rights to the project. Under the lease agreement, Campeau agreed to pay LPA
additional consideration if the BRA approved the sale of the Hayward Parcel.
Thereafter, LPA was not directly involved in negotiations regarding the
sale of the Hayward Parcel. Campeau began elaborate plans for a development called
"Boston Crossing," which included construction of a department store and office
tower on the Hayward Parcel, the rebuilding of the Phase I mall on its nearby parcel, and
the construction of an office tower above a rebuilt Jordan Marsh. During 1988,
representatives from Campeau and the BRA met repeatedly to negotiate about Campeau's
plans. When it became clear that Campeau could not secure BRA approval for the Boston
Crossing project by the expiration of LPA's option period, Campeau requested a further
extension of the drop dead date. The BRA refused to extend the January 1, 1989, deadline.
On December 19, 1988, Campeau's president sent a letter to Mayor Flynn describing the
current state of the project, renewing Campeau's request for an extension of the option
period, and informing Mayor Flynn that "we have no recourse but to officially notify
the city that we wish to complete the transaction and make payment immediately." On
December 30, 1988, Stephen Coyle, director of the BRA, responded. He stated that,
"once the development review process is complete, the City's parcel can be sold for
its fair reuse value," and noted that "by their own terms, prior agreements on
Hayward Place will expire on January 1, 1989. This event does not in our judgment alter
our willingness to work with you . . . it simply puts the question of the disposition of
Hayward Place in a current context."
LPA's option period expired on January 1, 1989. In June, 1989, the BRA
approved Campeau's "Boston Crossing" design, but by June, 1990, Campeau had
defaulted on its payments to LPA under the lease agreement and LPA terminated its lease
with Campeau. Manufacturers Hanover Trust Company, as lender, foreclosed on LPA's and
Campeau's interests in the Lafayette Place Mall in February, 1991, and the project
collapsed. On March 16, 1992, LPA filed suit against the city and the BRA. LPA alleged
that the city had breached the Tripartite Agreement by failing to work out the necessary
details to effect the transfer of the Hayward Parcel after LPA exercised its option to
buy, and LPA sought specific performance, or, alternatively, damages for breach of the
Tripartite Agreement. LPA also sought damages for breach of the implied covenant of good
faith and fair dealing, interference with contractual relations, and violation of G. L. c.
93A.
On October 21, 1994, a jury returned a verdict against the city and the
BRA. The jury found that there was a contract for the purchase of the Hayward Parcel, that
both the city and the BRA breached the contract, but that the BRA was not acting as an
agent of the city in connection with the contract. The jury awarded LPA $9.6 million
against the city. The jury also found that the BRA intentionally interfered with
contractual relations between LPA and Campeau, and awarded LPA $6.4 million in damages.
The trial judge then ruled that the $6.4 million verdict against the BRA was
"encompassed" within the $9.6 million award against the city. On August 17,
1995, the judge granted the BRA's motion for judgment notwithstanding the verdict, ruling
that the BRA is a public employer under the Massachusetts Tort Claims Act and is therefore
immune from suit for intentional torts. We granted LPA's application for direct appellate
review.
II
The city makes two principal arguments in this appeal: that the
Tripartite Agreement was too indefinite to constitute a binding contract, and that in any
event the city was not in breach. Although the city treats these as quite distinct
arguments we believe that they must be considered together to come to a fair and sensible
view of the arrangement between the parties and their dealings with each other pursuant to
it. There were certainly contingencies left open at the time that the parties concluded
the Tripartite Agreement, principally the price to be paid, the treatment of Avenue de
Lafayette and New Essex Street, and whether or not the city would choose to build an
underground garage on the Hayward Parcel. But these open matters did not preclude the
formation of a binding agreement. The parties specified formulae and procedures that would
determine a price under the several contingencies. It would be most unfortunate if parties
could not make binding, reliable agreements about such complex projects, allowing them to
make commitments and seek financing for their conclusion. If the degree of specificity the
city claims is necessary were insisted on, no such agreements could be concluded. But it
is the other side of this same coin that the procedures necessary to lend specificity to
what at the outset is not entirely specific are an integral part of the agreement the
parties concluded, and, if a party does not follow those procedures, it should not be able
to claim that the other side is in breach of what is necessarily still an open-ended
arrangement. We conclude that there was sufficient evidence to find a binding agreement,
as the jury indeed did find, but it is also clear, as a matter of law, that LPA failed to
follow the steps required of it under the Tripartite Agreement as supplemented to put the
city in breach.
A
The first question is whether there was a valid and enforceable
contract between LPA and the city or whether, as the city claims, the terms of the
Tripartite Agreement as amended were too indefinite to constitute a contract. The
Tripartite Agreement states that "the parties shall in good faith negotiate and enter
into an agreement," which the city argues indicates that no binding agreement had
been concluded. The city points out that Section 6.02 leaves undetermined the contract
price and exactly what is to be included in the Hayward Parcel. In some cases, the failure
to reduce uncertainties to definite terms is fatal, particularly where parties have not
yet formalized their negotiations or have left essential terms completely open. See Mendel
Kern, Inc. v. Workshop, Inc., 400 Mass. 277, 280-281, 508 N.E.2d 853 (1987) ("an
intention to do something is not necessarily a promise to do it"); Lucey v. Hero
Int'l Corp., 361 Mass. 569, 574, 281 N.E.2d 266 (1972) (no option contract for purchase of
land where parties merely specified boundaries to be "mutually agreed upon by both
parties"); Saxon Theatre Corp. v. Sage, 347 Mass. 662, 666, 200 N.E.2d 241 (1964) (no
contract for lease of property where parties merely signed letter of intent that provided
no description of the land nor means of determining rent). But see Shayeb v. Holland, 321
Mass. 429, 431, 73 N.E.2d 731 (1947) (enforcing contract despite absence of price term).
We adhere to the principle that "an agreement to reach an agreement is a
contradiction in terms and imposes no obligation on the parties thereto," Rosenfield
v. United States Trust Co., 290 Mass. 210, 217, 195 N.E. 323 (1935), in the circumstances
that justify and gave rise to it: where parties have merely reached the stage of
"imperfect negotiation" prior to formalizing a contract, and have not yet
reduced their agreement to terms. Id. When parties have progressed beyond that stage,
however, a competing principle applies: a contract should be interpreted "so as to
make it a valid and enforceable undertaking rather than one of no force and effect."
Shayeb v. Holland, supra at 432. See McMahon v. Monarch Life Ins. Co., 345 Mass. 261, 264,
186 N.E.2d 827 (1962). Rules of contract must not preclude parties from binding themselves
in the face of uncertainty. If parties specify formulae and procedures that, although
contingent on future events, provide mechanisms to narrow present uncertainties to rights
and obligations, their agreement is binding. See generally Hastings Assocs. v. Local 369
Bldg. Fund, Inc., 42 Mass. App. Ct. 162, 169, 675 N.E.2d 403 (1997) (accepting contract
calling for appointment of neutral third party to determine lease price under formula);
Cataldo v. Zuckerman, 20 Mass. App. Ct. 731, 737, 482 N.E.2d 849 (1985) (accepting formula
for determination of compensation as sufficiently specific to create contract).
The Tripartite Agreement provided a pricing formula to determine the
price to be paid for the Hayward Parcel. When the parties signed the Tripartite Agreement,
most of the information needed to complete that formula was available. Because the formula
incorporated the fair market value of the parcel at the time of the future transaction,
which, by definition, was unknown at the time of contracting, Section 13.01 detailed an
appraisal procedure to be used for securing that information. By using that procedure,
which called for the creation of a three-member appraisal board, the parties could have
determined the price to be paid. In addition, the Second Supplemental Agreement states
that "if the Developer shall exercise the right and option set forth in Section 6.02,
there shall automatically be created an agreement by the Developer to buy and the City to
sell" the Hayward Parcel. Moreover, it specified that "appropriate details of
the purchase and sale . . . shall be resolved by arbitration" in accordance with a
specified procedure. Although this provision was not added until 1982, it created a means
for resolving disputes that might arise in the course of effecting the ultimate sale of
the Hayward Parcel. In particular, questions about the exact size of the parcel and the
allocation of air rights over the relevant public streets were the kind of
"details" that could be worked out using this process. To borrow Justice
Holmes's metaphor, the machinery was built and had merely to be set in motion. See
Drummond v. Crane, 159 Mass. 577, 579, 35 N.E. 90 (1893) (a future writing was merely
"additional wheel in the machinery" of a contract). See also Sands v. Arruda,
359 Mass. 591, 594, 270 N.E.2d 826 (1971); Coan v. Holbrook, 327 Mass. 221, 224, 97 N.E.2d
649 (1951). We therefore conclude that the Tripartite Agreement, as amended, was an
enforceable contract, under which both parties had certain rights and obligations.
B
Because the Tripartite Agreement, as amended, was an enforceable
contract, upon LPA's exercise of its option in 1986, there arose a bilateral contract for
the purchase and sale of the Hayward Parcel. The question then becomes whether LPA
can, as a matter of law, maintain a claim against the city for breach of that contract.
"The general rule is that when performance under a contract is concurrent one party
cannot put the other in default unless he is ready, able, and willing to perform and has
manifested this by some offer of performance." Leigh v. Rule, 331 Mass. 664, 668, 121
N.E.2d 854 (1954). See 6 Corbin, Contracts § 1258 (1962). Any material failure by a
plaintiff to put a defendant in breach bars recovery, unless the plaintiff is excused from
tender because the other party has shown that he cannot or will not perform. Even if
a potential buyer notifies the seller of the buyer's intention to tender on a certain date
and appears at the registry of deeds on that date with the required consideration, there
may not be the "readiness to perform" that is a necessary condition of placing
the defendant in breach.
Applying these principles to the facts most favorable to LPA in this
case, the question becomes whether LPA, as a matter of law, was ready, able, and willing
to close the sale of the Hayward Parcel prior to January 1, 1989, and whether LPA
indicated as much to the city.
[The court concluded that LPA was not ready, able and willing to
close the sale, in part LPA had not initiated the appraisal process that the contract had
established to fix the purchase price.]
. . .
V
Because we conclude as a matter of law that the city did not breach its
contract with LPA, we reverse the judgment of the Superior Court and order entry of
judgment for the city. Whatever contractual claims LPA may have against the BRA must fail
for the same reason. The judgment in favor of the BRA is affirmed because we agree that it
is immune from suit for an intentional tort. The judgment in favor of the city and the BRA
dismissing LPA's c. 93A is also affirmed.
So ordered.