Totem Marine Tug & Barge, Inc. v. Alyeska Pipeline Service Co.
584 P.2d 15 (Alaska 1978)
Burke
This appeal arises from the superior court's granting of summary judgment in favor of
defendants-appellees Alyeska Pipeline Services, et al., in a contract action brought
by plaintiffs-appellants Totem Marine Tug & Barge, Inc., Pacific, Inc., and Richard
Stair.
The following summary of events is derived from the materials submitted
in the summary judgment proceedings below.
Totem is a closely held Alaska corporation which began operations in
March of 1975. Richard Stair, at all times relevant to this case, was vice-president of
Totem. In June of 1975, Totem entered into a contract with Alyeska under which Totem was
to transport pipeline construction materials from Houston, Texas, to a designated port in
southern Alaska, with the possibility of one or two cargo stops along the way. In order to
carry out this contract, which was Totem's first, Totem chartered a barge (The
"Marine Flasher") and an ocean-going tug (the "Kirt Chouest"). These
charters and other initial operations costs were made possible by loans to Totem from
Richard Stair individually and Pacific, Inc., a corporation of which Stair was principal
stockholder and officer, as well as by guarantees by Stair and Pacific.
By the terms of the contract, Totem was to have completed performance
by approximately August 15, 1975. From the start, however, there were numerous
problems which impeded Totem's performance of the contract. For example, according to
Totem, Alyeska represented that approximately 1,800 to 2,100 tons of regular uncoated pipe
were to be loaded in Houston, and that perhaps another 6,000 to 7,000 tons of materials
would be put on the barge at later stops along the west coast. Upon the arrival of the tug
and barge in Houston, however, Totem found that about 6,700 to 7,200 tons of coated pipe,
steel beams and valves, haphazardly and improperly piled, were in the yard to be loaded.
This situation called for remodeling of the barge and extra cranes and stevedores, and
resulted in the loading taking thirty days rather than the three days which Totem had
anticipated it would take to load 2,000 tons. The lengthy loading period was also caused
in part by Alyeska's delay in assuring Totem that it would pay for the additional
expenses, bad weather and other administrative problems.
The difficulties continued after the tug and barge left Houston. It
soon became apparent that the vessels were travelling more slowly than anticipated because
of the extra load. In response to Alyeska's complaints and with its verbal consent, on
August 13, 1975, Totem chartered a second tug, the "N. Joseph Guidry." When the
"Guidry" reached the Panama Canal, however, Alyeska had not yet furnished the
written amendment to the parties' contract. Afraid that Alyeska would not agree to cover
the cost of the second tug, Stair notified the "Guidry" not to go through the
Canal. After some discussions in which Alyeska complained of the delays and accused Totem
of lying about the horsepower of the first tug, Alyeska executed the amendment on August
21, 1975.
By this time the "Guidry" had lost its preferred passage
through the Canal and had to wait two or three additional days before it could go through.
Upon finally meeting, the three vessels encountered the tail of a hurricane which lasted
for about eight or nine days and which substantially impeded their progress.
The three vessels finally arrived in the vicinity of San Pedro,
California, where Totem planned to change crews and refuel. On Alyeska's orders, however,
the vessels instead pulled into port at Long Beach, California. At this point, Alyeska's
agents commenced off-loading the barge, without Totem's consent, without the necessary
load survey, and without a marine survey, the absence of which voided Totem's insurance.
After much wrangling and some concessions by Alyeska, the freight was off-loaded.
Thereafter, on or about September 14, 1975, Alyeska terminated the contract. The
termination was affirmed a few days later at a meeting at which Alyeska officials refused
to give a reason for the termination.
Following termination of the contract, Totem submitted termination
invoices to Alyeska and began pressing the latter for payment. The invoices came to
something between $260,000 and $300,000. An official from Alyeska told Totem that they
would look over the invoices but that they were not sure when payment would be made -
perhaps in a day or perhaps in six to eight months. Totem was in urgent need of cash as
the invoices represented debts which the company had incurred on 10-30 day payment
schedules. Totem's creditors were demanding payment and according to Stair, without
immediate cash, Totem would go bankrupt. Totem then turned over the collection to its
attorney, Roy Bell, directing him to advise Alyeska of Totem's financial straits.
Thereafter, Bell met with Alyeska officials in Seattle, and after some negotiations, Totem
received a settlement offer from Alyeska for $97,500. On November 6, 1975, Totem, through
its president Stair, signed an agreement releasing Alyeska from all claims by Totem
in exchange for $97,500.
On March 26, 1976, Totem, Richard Stair, and Pacific filed a complaint
against Alyeska, which was subsequently amended. In the amended complaint, the plaintiffs
sought to rescind the settlement and release on the ground of economic duress and to
recover the balance allegedly due on the original contract. In addition, they alleged that
Alyeska had wrongfully terminated the contract and sought miscellaneous other compensatory
and punitive damages.
Before filing an answer, Alyeska moved for summary judgment against the
plaintiffs on the ground that Totem had executed a binding release of all claims against
Alyeska and that as a matter of law, Totem could not prevail on its claim of economic
duress. In opposition, plaintiffs contended that the purported release was executed under
duress in that Alyeska wrongfully terminated the contract; that Alyeska knew that Totem
was faced with large debts and impending bankruptcy; that Alyeska withheld funds
admittedly owed knowing the effect this would have on plaintiffs and that plaintiffs had
no alternative but to involuntarily accept the $97,500 in order to avoid bankruptcy.
Plaintiffs maintained that they had thus raised genuine issues of material fact such that
trial was necessary, and that Alyeska was not entitled to judgment as a matter of law.
Alyeska disputed the plaintiffs' assertions.
On November 30, 1976, the superior court granted the defendant's motion
for summary judgment. This appeal followed.
. . .
II
As was noted above, a court's initial task in deciding motions for
summary judgment is to determine whether there exist genuine issues of material fact. In
order to decide whether such issues exist in this case, we must examine the doctrine
allowing avoidance of a release on grounds of economic duress.
This court has not yet decided a case involving a claim of economic
duress or what is also called business compulsion. At early common law, a contract could
be avoided on the ground of duress only if a party could show that the agreement was
entered into for fear of loss of life or limb, mayhem or imprisonment. 13 Williston on
Contracts, § 1601 at 649 (3d ed. Jaeger 1970). The threat had to be such as to overcome
the will of a person of ordinary firmness and courage. Id., § 1602 at 656. Subsequently,
however, the concept has been broadened to include myriad forms of economic coercion which
force a person to involuntarily enter into a particular transaction. The test has come to
be whether the will of the person induced by the threat was overcome rather than that of a
reasonably firm person. Id., § 1602 at 657.
At the outset it is helpful to acknowledge the various policy
considerations which are involved in cases involving economic duress. Typically, those
claiming such coercion are attempting to avoid the consequences of a modification of an
original contract or of a settlement and release agreement. On the one hand, courts
are reluctant to set aside agreements because of the notion of freedom of contract and
because of the desirability of having private dispute resolutions be final. On the other
hand, there is an increasing recognition of the law's role in correcting inequitable or
unequal exchanges between parties of disproportionate bargaining power and a greater
willingness to not enforce agreements which were entered into under coercive
circumstances. n3
There are various statements of what constitutes economic duress, but
as noted by one commentator, "The history of generalization in this field offers no
great encouragement for those who seek to summarize results in any single formula."
Dawson, Economic Duress - An Essay in Perspective, 45 Mich. L. Rev. 253, 289 (1947).
Section 492(b) of the Restatement [First] of Contracts defines duress as:
any wrongful threat of one person by words or other conduct that induces another to enter into a transaction under the influence of such fear as precludes him from exercising free will and judgment, if the threat was intended or should reasonably have been expected to operate as an inducement.
Professor Williston states the basic elements of economic duress in the following manner:
1. The party alleging economic duress must show that he has been the victim of a wrongful or unlawful act or threat, and
2. Such act or threat must be one which deprives the victim of his unfettered will.
13 Williston on Contracts, § 1617 at 704 [footnotes omitted].
Many courts state the test somewhat differently, eliminating use of the
vague term "free will," but retaining the same basic idea. Under this standard,
duress exists where: (1) one party involuntarily accepted the terms of another, (2)
circumstances permitted no other alternative, and (3) such circumstances were the result
of coercive acts of the other party. The third element is further explained as
follows:
In order to substantiate the allegation of economic duress or business compulsion, the plaintiff must go beyond the mere showing of reluctance to accept and of financial embarrassment. There must be a showing of acts on the part of the defendant which produced these two factors. The assertion of duress must be proven by evidence that the duress resulted from defendant's wrongful and oppressive conduct and not by the plaintiff's necessities.
W. R. Grimshaw Co., supra, 111 F. Supp. at 904.
As the above indicates, one essential element of economic duress is
that the plaintiff show that the other party by wrongful acts or threats, intentionally
caused him to involuntarily enter into a particular transaction. Courts have not attempted
to define exactly what constitutes a wrongful or coercive act, as wrongfulness depends on
the particular facts in each case. This requirement may be satisfied where the alleged
wrongdoer's conduct is criminal or tortious but an act or threat may also be considered
wrongful if it is wrongful in the moral sense.
In many cases, a threat to breach a contract or to withhold payment of
an admitted debt has constituted a wrongful act. Implicit in such cases is the
additional requirement that the threat to breach the contract or withhold payment be done
in bad faith.
Economic duress does not exist, however, merely because a person has
been the victim of a wrongful act; in addition, the victim must have no choice but to
agree to the other party's terms or face serious financial hardship. Thus, in order to
avoid a contract, a party must also show that he had no reasonable alternative to agreeing
to the other party's terms, or, as it is often stated, that he had no adequate remedy if
the threat were to be carried out. What constitutes a reasonable alternative is a
question of fact, depending on the circumstances of each case. An available legal remedy,
such as an action for breach of contract, may provide such an alternative. Where one party
wrongfully threatens to withhold goods, services or money from another unless certain
demands are met, the availability on the market of similar goods and services or of other
sources of funds may also provide an alternative to succumbing to the coercing party's
demands. Generally, it has been said that "the adequacy of the remedy is to be
tested by a practical standard which takes into consideration the exigencies of the
situation in which the alleged victim finds himself." Ross Systems, 173 A.2d at 262.
An available alternative or remedy may not be adequate where the delay
involved in pursuing that remedy would cause immediate and irreparable loss to one's
economic or business interest. For example, in Austin Instrument, supra, and Gallagher
Switchboard Corp. v. Heckler Electric Co., 36 Misc.2d 225, 232 N.Y.S.2d 590 (N.Y. Sup. Ct.
1962), duress was found in the following circumstances: A subcontractor threatened to
refuse further delivery under a contract unless the contractor agreed to modify the
existing contract between the parties. The contractor was unable to obtain the necessary
materials elsewhere without delay, and if it did not have the materials promptly, it would
have been in default on its main contract with the government. In each case such default
would have had grave economic consequences for the contractor and hence it agreed to the
modifications. In both, the courts found that the alternatives to agreeing to the
modification were inadequate (i.e., suing for breach of contract or obtaining the
materials elsewhere) and that modifications therefore were signed under duress and
voidable.
Professor Dalzell, in Duress By Economic Pressure II, 20 N. Carolina N.
Rev. 340, 370 (1942), notes the following with regard to the adequacy of legal remedies
where one party refuses to pay a contract claim:
Nowadays, a wait of even a few weeks in collecting on a contract claim is sometimes serious or fatal for an enterprise at a crisis in its history. The business of a creditor in financial straits is at the mercy of an unscrupulous debtor, who need only suggest that if the creditor does not care to settle on the debtor's own hard terms, he can sue. This situation, in which promptness in payment is vastly more important than even approximate justice in the settlement terms, is too common in modern business relations to be ignored by society and the courts.
This view finds support in Capps v. Georgia Pacific Corporation, 253
Or. 248, 453 P.2d 935 (1969). There, the plaintiff was owed $157,000 as a commission for
finding a lessee for defendant's property but in exchange for $5,000, the plaintiff signed
a release of his claim against defendant. The plaintiff sued for the balance of the
commission, alleging that the release had been executed under duress. His complaint,
however, was dismissed. On appeal, the court held that the plaintiff had stated a claim
where he alleged that he had accepted the grossly inadequate sum because he was in danger
of immediately losing his home by mortgage foreclosure and other property by foreclosure
and repossession if he did not obtain immediate funds from the defendant. One basis for
its holding was found in the following quote by a leading commentator in the area of
economic
duress:
The most that can be claimed [regarding the law of economic duress] is that change has been broadly toward acceptance of a general conclusion - that in the absence of specific countervailing factors of policy or administrative feasibility, restitution is required of any excessive gain that results, in a bargain transaction, from impaired bargaining power, whether the impairment consists of economic necessity, mental or physical disability, or a wide disparity in knowledge or experience.
Dawson, Economic Duress - An Essay In Perspective, 45 Mich. L. Rev. 253, 289 (1947). n4
III
Turning to the instant case, we believe that Totem's allegations, if
proved, would support a finding that it executed a release of its contract claims against
Alyeska under economic duress. Totem has alleged that Alyeska deliberately withheld
payment of an acknowledged debt, knowing that Totem had no choice but to accept an
inadequate sum in settlement of that debt; that Totem was faced with impending bankruptcy;
that Totem was unable to meet its pressing debts other than by accepting the immediate
cash payment offered by Alyeska; and that through necessity, Totem thus involuntarily
accepted an inadequate settlement offer from Alyeska and executed a release of all claims
under the contract. If the release was in fact executed under these circumstances, n5 we think that under the legal principles discussed above that
this would constitute the type of wrongful conduct and lack of alternatives that would
render the release voidable by Totem on the ground of economic duress. We would add that
although Totem need not necessarily prove its allegation that Alyeska's termination of the
contract was wrongful in order to sustain a claim of economic duress, the events leading
to the termination would be probative as to whether Alyeska exerted any wrongful pressure
on Totem and whether Alyeska wrongfully withheld payment from Totem.
One purpose of summary judgment, however, is to pierce the allegations
in the pleadings in an effort to determine whether genuine issues of fact exist. As the
moving party, Alyeska had the burden of showing that there were no such genuine issues and
that it was entitled to judgment as a matter of law. Alyeska showed that Totem had
executed the release, that Totem had been represented by counsel at the negotiating
session leading to the settlement and release and that appellant Stair, who actually
signed the release on behalf of Totem, was fully aware of the consequences of such a
release. Such evidence, by itself, would have entitled Alyeska to summary judgment in its
favor. As a matter of law, there is no doubt that a valid release of all claims arising
under a contract will bar any subsequent claims based on that contract.
To avoid summary judgment once the moving party meets its burden, the
non-moving party must produce competent evidence showing that there are issues of material
fact to be tried. The respondent must set forth specific facts showing that it could
produce admissible evidence reasonably tending to dispute the movants evidence or
establish an affirmative defense. The court then must draw all reasonable inferences in
favor of the non-moving party and against the movant.
In entering summary judgment against Totem, the court below reasoned as
follows:
The plaintiffs, specifically Mr. Stair, assert the release and settlement should be held for naught because of duress and coercion exerted upon him and his corporation by the defendants' action.
Mr. Stair fails to show that the release and settlement negotiated by his attorneys was involuntary on his part. Mr. Stair did not personally participate in the negotiations which resulted in the release and settlement. No affidavit or other suggestion of evidence has been submitted to demonstrate that upon trial the plaintiffs could sustain their burden of proof required to set aside the release and settlement.
As thus stated, the superior court's decision clearly misstated the
standard applicable on motions for summary judgment. A party opposing summary judgment
need not establish that he will ultimately prevail at trial. Although we may affirm a
trial court's grant of summary judgment if alternative grounds exist for upholding its
judgment, we do not believe that summary judgment was properly granted in this case.
Our examination of the materials presented by Totem in opposition to
Alyeska's motion for summary judgment leads us to conclude that Totem has made a
sufficient factual showing as to each of the elements of economic duress to withstand that
motion. There is no doubt that Alyeska disputes many of the factual allegations made by
Totem n7 and drawing all inferences in favor of Totem, we
believe that genuine issues of material fact exist in this case such that trial is
necessary. Admittedly, Totem's showing was somewhat weak in that, for example, it did not
produce the testimony of Roy Bell, the attorney who represented Totem in the negotiations
leading to the settlement and release. At trial, it will probably be necessary for Totem
to produce this evidence if it is to prevail on its claim of duress. However, a party
opposing a motion for summary judgment need not produce all of the evidence it may have at
its disposal but need only show that issues of material fact exist. Therefore, we hold
that the superior court erred in granting summary judgment for appellees and remand the
case to the superior court for trial in accordance with the legal principles set forth
above.
. . .
Reversed and remanded.