Jacob & Youngs v. Kent
230 N.Y. 239 (N.Y. Ct. of Appeals 1921)
Cardozo
The plaintiff built a country residence for the defendant at a cost of
upwards of $77,000 [Ed. $1,325,000 in 2001 dollars], and now sues to recover a balance of
$3,483.46 [$59,935 in 2001 dollars], remaining unpaid. The work of construction ceased in
June, 1914, and the defendant then began to occupy the dwelling. There was no complaint of
defective performance until March, 1915. One of the specifications for the plumbing work
provides that "all wrought iron pipe must be well galvanized, lap welded pipe of the
grade known as 'standard pipe' of Reading manufacture." The defendant learned in
March, 1915, that some of the pipe, instead of being made in Reading, was the product of
other factories. The plaintiff was accordingly directed by the architect to do the work
anew. The plumbing was then encased within the walls except in a few places
where it had to be exposed. Obedience to the order meant more than the substitution of
other pipe. It meant the demolition at great expense of substantial parts of the completed
structure. The plaintiff left the work untouched, and asked for a certificate that the
final payment was due. Refusal of the certificate was followed by this suit.
The evidence sustains a finding that the omission of the prescribed
brand of pipe was neither fraudulent nor willful. It was the result of the oversight and
inattention of the plaintiff's subcontractor. Reading pipe is distinguished from Cohoes
pipe and other brands only by the name of the manufacturer stamped upon it at intervals of
between six and seven feet. Even the defendant's architect, though he inspected the pipe
upon arrival, failed to notice the discrepancy. The plaintiff tried to show that the
brands installed, though made by other manufacturers, were the same in quality, in
appearance, in market value and in cost as the brand stated in the contract -- that they
were, indeed, the same thing, though manufactured in another place. The evidence was
excluded, and a verdict directed for the defendant. The Appellate Division reversed, and
granted a new trial.
We think the evidence, if admitted, would have supplied some basis for
the inference that the defect was insignificant in its relation to the project. The courts
never say that one who makes a contract fills the measure of his duty by less than full
performance. They do say, however, that an omission, both trivial and innocent, will
sometimes be atoned for by allowance of the resulting damage, and will not always be the
breach of a condition to be followed by a forfeiture. The distinction is akin
to that between dependent and independent promises, or between promises and conditions.
Some promises are so plainly independent that they can never by fair construction be
conditions of one another. Others are so plainly dependent that they must always be
conditions. Others, though dependent and thus conditions when there is departure in
point of substance, will be viewed as independent and collateral when the departure is
insignificant. Considerations partly of justice and partly of presumable intention are to
tell us whether this or that promise shall be placed in one class or in another. The
simple and the uniform will call for different remedies from the multifarious and the
intricate. The margin of departure within the range of normal expectation upon a sale of
common chattels will vary from the margin to be expected upon a contract for the
construction of a mansion or a "skyscraper." There will be harshness sometimes
and oppression in the implication of a condition when the thing upon which labor has been
expended is incapable of surrender because united to the land, and equity and reason in
the implication of a like condition when the subject-matter, if defective, is in shape to
be returned. From the conclusion that promises may not be treated as dependent to the
extent of their uttermost minutiae without a sacrifice of justice, the progress is a short
one to the conclusion that they may not be so treated without a perversion of intention.
Intention not otherwise revealed may be presumed to hold in contemplation the reasonable
and probable. If something else is in view, it must not be left to implication. There will
be no assumption of a purpose to visit venial faults with oppressive retribution.
Those who think more of symmetry and logic in the development of legal
rules than of practical adaptation to the attainment of a just result will be troubled by
a classification where the lines of division are so wavering and blurred. Something,
doubtless, may be said on the score of consistency and certainty in favor of a stricter
standard. The courts have balanced such considerations against those of equity and
fairness, and found the latter to be the weightier. The decisions in this state commit us
to the liberal view, which is making its way, nowadays, in jurisdictions slow to welcome
it. Where the line is to be drawn between the important and the trivial cannot
be settled by a formula. "In the nature of the case precise boundaries are
impossible" (2 Williston on Contracts, sec. 841). The same omission may take on one
aspect or another according to its setting. Substitution of equivalents may not have the
same significance in fields of art on the one side and in those of mere utility on the
other. Nowhere will change be tolerated, however, if it is so dominant or pervasive as in
any real or substantial measure to frustrate the purpose of the contract.
There is no general license to install whatever, in the builder's judgment, may be
regarded as "just as good." The question is one of degree, to be answered,
if there is doubt, by the triers of the facts, and, if the inferences are certain, by the
judges of the law. We must weigh the purpose to be served, the
desire to be gratified, the excuse for deviation from the letter, the cruelty of enforced
adherence. Then only can we tell whether literal fulfilment is to be implied by law as
a condition. This is not to say that the parties are
not free by apt and certain words to effectuate a purpose that performance of every term
shall be a condition of recovery. That question is not here. This is merely to say
that the law will be slow to impute the purpose, in the silence of the parties, where the
significance of the default is grievously out of proportion to the oppression of the
forfeiture. The willful transgressor must accept the penalty of his transgression. For him
there is no occasion to mitigate the rigor of implied conditions. The transgressor whose
default is unintentional and trivial may hope for mercy if he will offer atonement for his
wrong.
In the circumstances of this case, we think the measure of the
allowance is not the cost of replacement, which would be great, but the difference in
value, which would be either nominal or nothing. Some of the exposed sections might
perhaps have been replaced at moderate expense. The defendant did not limit his demand to
them, but treated the plumbing as a unit to be corrected from cellar to roof. In point of
fact, the plaintiff never reached the stage at which evidence of the extent of the
allowance became necessary. The trial court had excluded evidence that the defect was
unsubstantial, and in view of that ruling there was no occasion for the plaintiff to go
farther with an offer of proof. We think, however, that the offer, if it had been made,
would not of necessity have been defective because directed to difference in value. It is
true that in most cases the cost of replacement is the measure. The owner is entitled to
the money which will permit him to complete, unless the cost of completion is grossly and
unfairly out of proportion to the good to be attained. When that is true, the measure is
the difference in value. Specifications call, let us say, for a foundation built of
granite quarried in Vermont. On the completion of the building, the owner learns that
through the blunder of a subcontractor part of the foundation has been built of granite of
the same quality quarried in New Hampshire. The measure of allowance is not the cost of
reconstruction. "There may be omissions of that which could not afterwards be
supplied exactly as called for by the contract without taking down the building to its
foundations, and at the same time the omission may not affect the value of the building
for use or otherwise, except so slightly as to be hardly appreciable." The rule
that gives a remedy in cases of substantial performance with compensation for defects of
trivial or inappreciable importance, has been developed by the courts as an instrument of
justice. The measure of the allowance must be shaped to the same end.
The order should be affirmed, and judgment absolute directed in favor
of the plaintiff upon the stipulation, with costs in all courts.
McLaughlin, J. (dissenting).
I dissent. The plaintiff did not perform its contract. Its failure
to do so was either intentional or due to gross neglect which, under the uncontradicted
facts, amounted to the same thing, nor did it make any proof of the cost of compliance,
where compliance was possible.
Under its contract it obligated itself to use in the plumbing only pipe
(between 2,000 and 2,500 feet) made by the Reading Manufacturing Company. The first pipe
delivered was about 1,000 feet and the plaintiff's superintendent then called the
attention of the foreman of the subcontractor, who was doing the plumbing, to the fact
that the specifications annexed to the contract required all pipe used in the plumbing to
be of the Reading Manufacturing Company. They then examined it for the purpose of
ascertaining whether this delivery was of that manufacture and found it was. Thereafter,
as pipe was required in the progress of the work, the foreman of the subcontractor would
leave word at its shop that he wanted a specified number of feet of pipe, without in any
way indicating of what manufacture. Pipe would thereafter be delivered and installed in
the building, without any examination whatever. Indeed, no examination, so far as appears,
was made by the plaintiff, the subcontractor, defendant's architect, or any one else, of
any of the pipe except the first delivery, until after the building had been completed.
Plaintiff's architect then refused to give the certificate of completion, upon which the
final payment depended, because all of the pipe used in the plumbing was not of the kind
called for by the contract. After such refusal, the subcontractor removed the covering or
insulation from about 900 feet of pipe which was exposed in the basement, cellar and
attic, and all but 70 feet was found to have been manufactured, not by the Reading
Company, but by other manufacturers, some by the Cohoes Rolling Mill Company, some by the
National Steel Works, some by the South Chester Tubing Company, and some which bore no
manufacturer's mark at all. The balance of the pipe had been so installed in the building
that an inspection of it could not be had without demolishing, in part at least, the
building itself.
I am of the opinion the trial court was right in directing a verdict
for the defendant. The plaintiff agreed that all the pipe used should be of the Reading
Manufacturing Company. Only about two-fifths of it, so far as appears, was of that kind.
If more were used, then the burden of proving that fact was upon the plaintiff, which it
could easily have done, since it knew where the pipe was obtained. The question of
substantial performance of a contract of the character of the one under consideration
depends in no small degree upon the good faith of the contractor. If the plaintiff had
intended to, and had complied with the terms of the contract except as to minor omissions,
due to inadvertence, then he might be allowed to recover the contract price, less the
amount necessary to fully compensate the defendant for damages caused by such
omissions. But that is not this case. It installed between 2,000 and 2,500 feet of
pipe, of which only 1,000 feet at most complied with the contract. No explanation was
given why pipe called for by the contract was not used, nor was any effort made to show
what it would cost to remove the pipe of other manufacturers and install that of the
Reading Manufacturing Company. The defendant had a right to contract for what he wanted.
He had a right before making payment to get what the contract called for. It is no answer
to this suggestion to say that the pipe put in was just as good as that made by the
Reading Manufacturing Company, or that the difference in value between such pipe and the
pipe made by the Reading Manufacturing Company would be either "nominal or
nothing." Defendant contracted for pipe made by the Reading Manufacturing
Company. What his reason was for requiring this kind of pipe is of no importance. He
wanted that and was entitled to it. It may have been a mere whim on his part, but even so,
he had a right to this kind of pipe, regardless of whether some other kind, according to
the opinion of the contractor or experts, would have been "just as good, better, or
done just as well." He agreed to pay only upon condition that the pipe installed were
made by that company and he ought not to be compelled to pay unless that condition be
performed. The rule, therefore, of substantial performance, with damages for
unsubstantial omissions, has no application.
What was said by this court in Smith v. Brady (supra) is quite
applicable here: "I suppose it will be conceded that everyone has a right to build
his house, his cottage or his store after such a model and in such style as shall best
accord with his notions of utility or be most agreeable to his fancy. The specifications
of the contract become the law between the parties until voluntarily changed. If the owner
prefers a plain and simple Doric column, and has so provided in the agreement, the
contractor has no right to put in its place the more costly and elegant Corinthian.
If the owner, having regard to strength and durability, has contracted for walls of
specified materials to be laid in a particular manner, or for a given number of joists and
beams, the builder has no right to substitute his own judgment or that of others. Having
departed from the agreement, if performance has not been waived by the other party, the
law will not allow him to allege that he has made as good a building as the one he engaged
to erect. He can demand payment only upon and according to the terms of his contract, and
if the conditions on which payment is due have not been performed, then the right to
demand it does not exist. To hold a different doctrine would be simply to make another
contract, and would be giving to parties an encouragement to violate their engagements,
which the just policy of the law does not permit." (p. 186.)
I am of the opinion the trial court did not err in ruling on the
admission of evidence or in directing a verdict for the defendant.
For the foregoing reasons I think the judgment of the Appellate
Division should be reversed and the judgment of the Trial Term affirmed.